At the beginning of 2018, the MKG team put into operation a greenfield power plant in Veendam, Netherlands, located directly at the Wildervanck canal. The in-time finalisation of the project was by no means guaranteed: Unlike with the dessert project in Iran, water and mud created unfavourable conditions for both, men and machines.

Project data

  • 15.5 MWp / 57,288 modules
  • System: GMS® MAX II-6H
  • September 2017 – January 2018
Solar park Veendam (NL)