Challenges are part of the job – and so are the right solutions: At our Uissigheim project, uneven terrain and difficult ground conditions created additional challenges for both planning and execution. Thanks to the use of our balancing rocker system, the uneven ground could be compensated efficiently, ensuring a reliable and smooth installation process.
Project data
- 49 MWp / 69,048 modules
- System: GMS® SCALE II-3V
- Service package 3 (delivery, ramming + mechanical assembly, DC installation)
- August 2025 – March 2026
- Client: Soventix GmbH